ESTIMATION - Practice Mode

1) Which estimate is prepared while the expenditure on a work exceeds by more than 10%?
Correct Answer: Revised
2) Which estimate is prepared while the original sanctional estimate is exceeded by more than 5%?
Correct Answer: Revised
3) Which estimate is prepared for the technical sanction of the competent authority?
Correct Answer: Detailed