ESTIMATION - Practice Mode
1) Which is the builtup covered are of a building measured at the floor level?
Correct Answer: Plinth area
2) Which estimate is required to decide the financial position and policy for the administrative sanction?
Correct Answer: Preliminary
3) What is the range of contingencies in an approximate or preliminary Estimate?
Correct Answer: 5%-10%
4) Which approval authorises the engineering department to take up the work?
Correct Answer: Administrative
5) Which means the sanction of the detailed estimate by the competent authority of the engineering department?
Correct Answer: Technical sanction