TEMPORARY STRUCTURE - Practice Mode

1) What is the approximate depth of vertical sheeting adopted in timbering in soft ground?
Correct Answer: 10m
2) What is the minimum period for the removal of props to beams and arches for a span of 6m in centrering / form work?
Correct Answer: 14 Days
3) What is the maximum suitable distance between the two adjacent parallel walls for single flying shore?
Correct Answer: 9 m
4) Which shoreing is suitable, for existing foundations to be depended?
Correct Answer: Dead shore
5) How to rectify if settlement of existing foundation has taken place?
Correct Answer: Under pinning