1) What is the out-turn of mason constructing stone arch work?
Correct Answer: 0.40 cu.m
Explanation:

.

2) What is the out-turn of mason, constructing superstructure with brick masonry?
Correct Answer: 1.00 cu.m
3) What percentage contractors profit is included in the analysis of rate?
Correct Answer: 10
4) What quantity bitumen is required for 100m2 first coat painting on DPC?
Correct Answer: 150 kg
5) What quantity of stone is required for 1m3 of rubble masonary?
Correct Answer: 1.25 cu.m