1) Which is rough cost estimate?
Revised estimate
Annual repair estimate
Plinth area estimate
Supplementary estimate
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Plinth area estimate
Question Details
1) Which is rough cost estimate?
Revised estimate
Annual repair estimate
Plinth area estimate
Supplementary estimate
2) Which is an item rate estimate?
Plinth area
Annual repair
Cubical content
Preliminary
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Annual repair
Question Details
2) Which is an item rate estimate?
Plinth area
Annual repair
Cubical content
Preliminary
3) What is the sequence of booking measurements?
Breadth, length and depth
Number, length and depth
Diameter, length and density
Length, breadth and height
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Length, breadth and height
Question Details
3) What is the sequence of booking measurements?
Breadth, length and depth
Number, length and depth
Diameter, length and density
Length, breadth and height
4) What is the minimum length for bill quantity calculation?
0.5 mm
1 mm
1cm
10 cm
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 1 mm
Question Details
4) What is the minimum length for bill quantity calculation?
0.5 mm
1 mm
1cm
10 cm
5) What is the minimum area for bill quantity calculation?
1 mm<sup>2</sup>
1 cm<sup>2</sup>
0.01 sq.m
1m<sup>2</sup>
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 0.01 sq.m
Question Details
5) What is the minimum area for bill quantity calculation?
1 mm<sup>2</sup>
1 cm<sup>2</sup>
0.01 sq.m
1m<sup>2</sup>