1) Which formula used for calculate more accurately the quantity of earth work in embankment and cutting?
Average depth method
Average cross sectional area method
Prismoidal
Mid area method
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Prismoidal
Question Details
1) Which formula used for calculate more accurately the quantity of earth work in embankment and cutting?
Average depth method
Average cross sectional area method
Prismoidal