ESTIMATION - Quiz
Categories
Surveyor
ESTIMATION
1) Which is the builtup covered are of a building measured at the floor level?
Floor area
Carpet area
Plinth area
Circulation area
2) Which estimate is required to decide the financial position and policy for the administrative sanction?
Preliminary
Detailed
Supplementary
Revised
3) What is the range of contingencies in an approximate or preliminary Estimate?
5%-8%
5%-7%
5%-10%
0.1
4) Which approval authorises the engineering department to take up the work?
Administrative
Technical
Expenditure
Schedule
5) Which means the sanction of the detailed estimate by the competent authority of the engineering department?
Administrative sanction
Expenditure sanction
Technical sanction
Administrative approval